Industry Reports

Weekly briefs and monthly reports on AI compute, data centres and the power behind them: what moved, what it means for the build-out, and what to watch next. Prepared by Vailinor Analysts from public sources.

Weekly briefs

Monthly reports, 2026

Coverage: September 2026

FERC delays PJM's backstop as AI compute contracts reach filings

FERC accepted PJM's backstop procurement but suspended it to February 2027, and its order recorded the market monitor's estimate that 4,017 MW of data-centre load had been cancelled or delayed. Nscale's listing filing disclosed up to US$44.6 billion of agreements with Anthropic at a West Virginia campus it says can deliver up to 8 GW of behind-the-meter power, with financing not yet committed, while Oracle reported US$288 billion of data-centre leases not yet started.

Read the report →
Coverage: August 2026

Texas audits its data-centre queue as large campuses plan their own power

Texas ordered an audit of every data centre in ERCOT's connection queue, FERC gave grid operators until November to answer its large-load orders, and PJM proposed curtailing new large loads first in emergencies when they do not bring enough capacity of their own. NVIDIA guaranteed leases covering 4.25 GW of IT load at an Ohio campus, and TrendForce projected that memory will take a growing share of cloud providers' capital spending.

Read the report →
Coverage: July 2026

PJM's auction falls short and new large loads are asked to bring their own capacity

PJM's capacity auction cleared at its price cap and short of its reliability requirement, and its board proposed that new large loads without their own capacity take a curtailable service. Alphabet and Amazon raised their spending plans, Amazon partly on memory prices, while TSMC said packaging capacity now limits its customers' growth.

Read the report →
Coverage: June 2026

FERC puts co-location on the table in grid rule reviews as dedicated power deals grow

FERC ordered six US grid operators to justify or rewrite their rules for connecting large loads, with co-location and behind-the-meter generation among the reform areas for five of them, and Chevron agreed a 20-year deal to supply a Microsoft data centre from a planned co-located gas plant of about 2.67 GW. SpaceX listed with AI compute first among its uses of proceeds, Korea set out an 18.4 GW AI data-centre plan with at least 8 GW of power pledged, and China's new energy plan pushes computing centres toward green-power direct connections.

Read the report →
Coverage: May 2026

An AI cluster can run on its own gas plant as regulators in several countries move on large-load rules

SpaceX's S-1 disclosed that its Colossus II cluster can run entirely on its own behind-the-meter gas plant, and that Anthropic has agreed to pay US$1.25 billion a month for compute after a reduced-fee ramp, under agreements either side can end on 90 days' notice. NERC issued a Level 3 alert on data-centre loads, Korea passed its AI Data Center Special Act, China published a plan tying AI compute to clean power, and Tenaga Nasional reported about 1 GW of actual data-centre load on its system against about 4.5 GW of maximum demand.

Read the report →
Coverage: April 2026

Hyperscaler spending moves higher and South-East Asian deals turn on power

Microsoft guided to roughly US$190 billion of capital expenditure in 2026, including about US$25 billion from higher component prices, Meta raised its range to US$125 billion to US$145 billion, and Anthropic committed to up to 5 GW from Amazon and about 3.5 GW through Broadcom, the latter dependent on its commercial success. FERC accepted part and rejected part of PJM's co-location compliance filing and said it intends to act on large-load interconnection by the end of June, while in South-East Asia several land and campus deals were tied to power, from DayOne's signed 511 MVA agreement in Batam to a Johor land purchase conditional on Data Centre Task Force approval and a TNB power letter.

Read the report →
Coverage: March 2026

The ratepayer pledge is signed and big AI campuses bring their own generation

Seven of the largest AI and cloud companies signed a White House pledge on 4 March to cover the cost of the new generation their data centres need, and by month end Crusoe had announced a 900 MW campus for Microsoft with a dedicated 900 MW on-site plant while Meta agreed to fund seven more utility gas plants in Louisiana. Rule-makers moved to set terms for grid access, with Texas proposing security and a fee of US$50,000 per MW each for large loads, and Australia drafting connection standards and setting national expectations for data centres.

Read the report →
Coverage: February 2026

Spending plans jump and big tech is told to bring its own power

Alphabet guided 2026 capital expenditure to US$175 billion to US$185 billion and Amazon to about US$200 billion, and OpenAI announced US$110 billion of new investment, part of it conditional, alongside 3 GW of dedicated NVIDIA inference capacity. Power stayed the constraint, with the US President calling on large tech companies to provide their own power, PJM proposing terms for co-located load and Malaysia saying it has been limiting approvals for new data centres not linked to AI.

Read the report →
Coverage: January 2026

Grid access comes with more conditions

In January, access to grid power for large data-centre loads was increasingly tied to conditions, led by PJM's move toward curtailing new load that does not bring its own generation, while Malaysia's penalty on data centres that use less than 85% of their declared demand drew fresh attention. Capital kept coming regardless, with Meta guiding 2026 capital expenditure to as much as US$135 billion, DayOne raising more than US$2 billion and Digital Edge committing US$4.5 billion in Greater Jakarta.

Read the report →
October 2026

In preparation

November 2026

In preparation

December 2026

In preparation