Firmus pulled its IPO and DayOne's US listing filing sorted its capacity by stage, with 962 MW in service and 1,328 MW under construction within about 2.3 GW of customer bookings, while FERC rejected the core of PJM's plan for connecting large loads. US opposition reached council votes and the November ballot, and regulators halted site work in Finland and West Java over missing environmental approvals.
Download the PDF ↓Key numbers
- DayOne had 962 MW of IT capacity in service on 20 September and 1,328 MW under construction, within about 2.3 GW of customer bookings. It also reported 2.3 GW of land with power approvals secured and a further 1.3 GW pipeline on sites that do not yet have them (F-1, filed 5 October).
- Firmus had 46 MW operating out of 912 MW scheduled, as a fund manager quoted by the Sydney Morning Herald put it after the IPO was withdrawn on 9 October.
- Heatmap counted at least US$260 billion of US data-centre investment cancelled in 2026 after local opposition, about half of it in the third quarter.
- A planned data centre in Reading has a 60 MW grid connection that waits on reinforcement due in 2037, so the developer plans 49.9 MW of fuel cells.
What moved this week
FERC rejects the core of PJM's plan for connecting large loads (30 September to 9 October)
FERC on 9 October rejected the Interim Resource Adequacy Service at the centre of PJM's large-load proposal, the interim route that would have let new large loads connect without matching new capacity if they agreed to be curtailed ahead of grid emergencies, and approved PJM's definition of a large load and its large-load registry, while also rejecting its "bring your own new capacity" rules, Utility Dive reported. PJM had said on 30 September that its reliability backstop procurement would not start that day, because FERC had accepted it but suspended it to 28 February 2027 pending further proceedings; a PJM spokesman later said it plans a revised filing by 29 October.
Why it matters. The rejected service was the one route in PJM's plan for a large load to connect before matching capacity exists. Large loads in PJM still have no agreed rule on who pays for new supply or who is cut first in an emergency, and contracts that assume a PJM connection carry that rule risk until PJM refiles and FERC rules again.
Firmus pulls its listing as DayOne files one that sorts capacity by stage (5 to 9 October)
Firmus withdrew its planned ASX listing on 9 October after cutting the offer price, and its board said proceeding was not in the best interests of the company and its shareholders; it will seek private capital. Minotaur Capital's Armina Rosenberg told the Sydney Morning Herald that Firmus had "46 megawatts operating out of 912 megawatts scheduled". Four days earlier DayOne filed for a Nasdaq listing with a prospectus that sorts its IT capacity by stage: 962 MW in service as of 20 September, 1,328 MW under construction, about 2.3 GW of customer bookings including the capacity in service, and a 1.3 GW pipeline on sites under sale agreements or letters of intent for which it has "not yet obtained the required power approvals or other permits".
Why it matters. Firmus's prospective investors raised several objections, the price and the overhang of existing shareholders among them, but the capacity point a fund manager made in public was 46 MW operating out of 912 MW scheduled. DayOne's filing, which separates capacity in service from booked capacity still being built and from sites still waiting on power approvals, shows the level of disclosure we expect investors to start asking every developer for.
US opposition to data centres reaches council votes and the ballot (2 to 8 October)
Heatmap counted at least US$260 billion of US data-centre investment cancelled this year after sustained local opposition, about US$130 billion of it in the third quarter, and about US$1 trillion facing sustained or meaningful opposition; its figures are announced values, which it says are likely an undercount. On 6 October San Francisco's supervisors and Oakland's council each passed a 45-day moratorium on new data centres, and Memphis postponed its vote on a proposed moratorium to 20 October. Ballotpedia counts at least 39 local data-centre measures this year, 35 of them on the 3 November ballot and 21 in Ohio, Newsweek reported, and a UMBC poll found 78% of the Maryland likely voters asked about statewide construction opposed new data centres. Amazon pledged on 2 October more than US$1 billion over five years for host communities.
Why it matters. Opposition that showed up in polls through the summer is now reaching council votes, and the 3 November ballots put a date on the next test; in the four local measures already decided this year, the outcome favoured tighter restrictions each time, Newsweek reported. AWS's chief executive linked the Amazon pledge to local opposition, saying more than 100 data-centre moratoriums are under consideration.
Environmental approvals halt site work in Finland and West Java (1 to 8 October)
Finland's licensing and supervisory authority told a Google subsidiary on 6 October to stop tree removal, excavation and road building at two planned data-centre sites, at Muhos and Kajaani, until environmental impact assessments are complete, while planning and surveys may continue; Google said it had not met the standards it set itself. In Indonesia, work remained stopped in early October at BDx's Jatiluhur campus in West Java, planned to scale to 640 MW with a first 120 MW building, which broke ground on 22 September, after the provincial governor ordered a halt until its environmental assessment and building permit are issued. BDx says it still targets operation in 2027.
Why it matters. Both projects had land, a plan and work under way, and an environmental assessment or building permit that had not yet been granted was enough to stop the site work.
Power is contracted now for delivery from 2027 to 2032 (30 September to 6 October)
Google signed a 20-year agreement with Constellation supporting about US$4.3 billion of upgrades that add 890 MW at 11 existing reactors by the end of 2032, the first by 2028, plus a separate 15-year agreement for 2,700 MW of existing output, POWER reported. Amazon's 20-year, 690 MW agreement at Calvert Cliffs, announced after the US close on 30 September, includes a 190 MW uprate due between 2030 and 2032. Black Hills agreed to serve a planned Google data centre in Cheyenne from late 2027, ramping to peak load in 2030, from a 2.7 GW resource mix including reserve margins, about 2.1 GW of it managed through a private microgrid. In Japan, JERA, Dell and RHAELM signed a memorandum on 1 October for an AI campus supported by up to 400 MW at JERA's Chiba thermal power station, which JERA says will be behind the meter, "enabling capacity to be delivered years ahead of a conventional grid-connected development schedule", with operations targeted around 2028.
Why it matters. Little of the new capacity announced this week will flow before 2028, and much of the headline volume is existing output changing hands. JERA's case for Chiba was speed: running the campus behind the meter from an operating power station, it says, will deliver capacity years ahead of a grid-connected schedule, a claim that for now rests on a memorandum.
Memory makers report record margins and supply committed into 2027 (30 September to 8 October)
Micron reported fiscal fourth-quarter revenue of US$54.23 billion after the US market close on 30 September, with a GAAP gross margin of 86.8% and guidance of US$61.5 billion, plus or minus US$1.5 billion, for the current quarter, and said it had completed agreements for the vast majority of its calendar 2027 HBM supply "with significant price increases year over year". Samsung guided to preliminary third-quarter operating profit of about KRW107.4 trillion, the first Korean company above KRW100 trillion in a quarter, The Korea Times reported, TSMC's September revenue rose 54.6% on a year earlier, and AMD and Huawei both said demand exceeds what they can supply.
Why it matters. This is the main counter-evidence to a power-first reading of the build-out: memory, packaging and wafers are scarce too, and memory makers are earning scarcity margins. Micron expects the industry to stay supply constrained through 2027 and 2028 and says it has no line of sight to when supply and demand return to balance. Our reading is that this shortage sits with a few companies spending on fabs, while grid and consent constraints depend on permits, elections and transmission decisions no single company controls, though on Micron's own timetable both run past 2028.
Singapore licenses data centres as Malaysia's regulator flags grid payback risk (7 to 9 October)
Singapore's Parliament passed the Digital Infrastructure Bill on 7 October. Every data centre of 3 MW of critical IT load or more will need a licence, and the regulator can write the efficiency and green-energy commitments operators made in capacity tenders into those licences; the Act is not yet in force, and its efficiency targets will come in regulations. In Malaysia, the Energy Commission's chief executive said, in remarks reported on 7 October, that data centres have pushed electricity demand growth to about 10%, and that grid investment recovered over about 20 years sits against commitments of 15 years from some operators and five to six years from colocation operators. Malaysia's budget on 9 October included RM15 billion of grid investment by TNB.
Why it matters. Singapore has written licence terms into law, and Malaysia's regulator has put the mismatch between grid paybacks and tenant commitments on the record. That mismatch is where stranded-cost risk sits, and we expect it to show up in tariffs and connection conditions.
Our reading of the week
This section gives our own reading of the week's events. Vailinor builds power-anchored, behind-the-meter compute, so we have an interest in the argument.
Our view is that the AI build-out is priced on signed capacity, while the constraint runs further up a chain: public and regulatory consent, then a grid connection, then energised power, and only then compute. This week produced evidence at the consent, grid and power links: the US cancellations and moratoriums and the Finnish and Indonesian permit halts above, Reading's 2037 grid date, a refiled grid application for the 1.3 GW Wisconsin campus Oracle is to lease, which research firm Aterio says "points to the potential for dates later than company guidance", and the distance between Firmus's operating and scheduled capacity.
The case against this reading has substance. Goldman Sachs kept its US data-centre outlook largely unchanged, raising its 2026 year-end estimate by 5 GW to 64 GW while cutting 2027 by 5 GW to 90 GW. Micron says the memory shortage has no visible end. DayOne's figures for Singapore, Johor and the Riau Islands show in-service capacity rising from 118 MW at the end of 2024 to 862 MW in September, with billings tracking it almost exactly, so in that corridor booked capacity has been turning into billed capacity at pace. A council can still say yes: in Taylor, Texas, the city council voted unanimously on 8 October, over objections from many residents at the meeting, to approve an agreement annexing a planned data-centre campus with an on-site power plant, which comes with an estimated US$28.2 million of community investment, KUT reported.
For anyone pricing this sector, our first reading is that a megawatt should be valued by where it sits on the chain: in service, under construction, on land with power approvals secured, or on land still waiting for them. DayOne's prospectus already sorts its capacity in close to these stages. Our second reading is that time goes to capacity whose approvals, connection and power are already in place, and that developers who can show this site by site will find it easier to raise money. Bridging with trucked or on-site gas buys time but brings its own approvals: Bloomberg reported, citing unnamed people, that Oracle has trucked compressed natural gas to sites in Utah and Texas while pipelines are built, and that the pipeline it is waiting for in New Mexico slipped into next year after state regulators rejected its original route.
Capital and valuation read-through
US borrowing costs rose over the same days that AI companies went looking for more capital. The US 10-year Treasury yield touched 5.34% on 1 October, its highest since 2002, before easing, and Reuters cited competition for capital from AI and data-centre construction as one driver. OpenAI is in talks to raise about US$30 billion at a pre-money valuation of about US$1.4 trillion, with UAE funds including MGX, and BlackRock, discussed as anchors, Bloomberg reported, and SpaceX is seeking about US$40 billion of debt led by Apollo to fund an Nvidia chip order, the FT reported; neither deal has closed. For a developer funding construction with debt, a higher rate raises the cost of each month a contracted site waits for power.
What we are watching
- PJM's special Members Committee meeting on 22 October and its revised backstop filing, planned by 29 October.
- Memphis's vote on a proposed data-centre moratorium on 20 October, and the 35 local data-centre measures on the 3 November ballot.
- Google's written response to Finland's authority, due 14 October, with the work suspension in effect by 23 October.
- Samsung's full third-quarter results on 29 October, for whether memory pricing keeps rising.
Sources
- DayOne Data Centers Ltd, Form F-1, 5 October 2026. sec.gov
- The Sydney Morning Herald, "Oliver Curtis' bid to float Firmus for $44 billion falls over", 9 October 2026. smh.com.au
- DatacenterDynamics, "Neocloud Firmus cancels IPO, blames market volatility", 9 October 2026. datacenterdynamics.com
- DatacenterDynamics, "Firmus drops IPO share price amid weak demand: report", 7 October 2026. datacenterdynamics.com
- Utility Dive, "FERC rejects most of PJM's large load interconnection plan", 12 October 2026 (on the order of 9 October). utilitydive.com
- PJM Inside Lines, "FERC Accepts PJM Reliability Backstop Proposal", 30 September 2026. insidelines.pjm.com
- Utility Dive, "DOE presses PJM on ratepayer protections from large load costs", 8 October 2026. utilitydive.com
- Heatmap, "Exclusive: Data Center Cancellations Top $260 Billion in 2026", 6 October 2026. heatmap.news
- Mission Local, "San Francisco supervisors pass 45-day data-center moratorium", 6 October 2026. missionlocal.org
- SFist, "San Francisco, Oakland pass 45-day moratoriums on new data centers", 7 October 2026. sfist.com
- WSMV, "Data center moratorium vote postponed after fight, protests", 6 October 2026. wsmv.com
- Newsweek, "Ohio Has Half of US Data Center Ballot Measures in Midterms", 5 October 2026. newsweek.com
- Fox Baltimore, "UMBC Poll finds widespread opposition to new data centers in Maryland", 8 October 2026. foxbaltimore.com
- The Next Web, "Amazon pledges $1bn over five years to US data centre communities", 2 October 2026. thenextweb.com
- Data Center Knowledge, "Permits, Not Power, Halt Google's Finland Data Centers", 8 October 2026. datacenterknowledge.com
- The Star (Xinhua), "Finnish authority halts work at Google data center sites over environmental assessment", 7 October 2026. thestar.com.my
- The Star (Reuters), "Indonesian governor orders halt on data centre project by Singapore's BDx due to lack of permits", 30 September 2026. thestar.com.my
- W.Media, "Indonesia pauses BDx Data Centers construction pending required permits and EIA report", 1 October 2026. w.media
- Bisnis.com, report on the BDx Jatiluhur halt (Indonesian), 5 October 2026. bisnis.com
- POWER Magazine, "Google deal backs 890 MW of Constellation nuclear uprates at 11 PJM reactors", 7 October 2026. powermag.com
- NeutronBytes, "Google's 20-Year $4.3 Billion Deal with Constellation to Uprate 11 Reactors", 9 October 2026. neutronbytes.com
- Constellation, "Constellation and Amazon Announce 20-Year Power Purchase Agreement Adding 190 Megawatts of Nuclear Capacity at Calvert Cliffs", 30 September 2026. constellationenergy.com
- Benzinga (Business Wire), Constellation and Amazon release, 30 September 2026, 16:00 EDT. benzinga.com
- Black Hills Corp., Form 8-K, Exhibit 99.1, 6 October 2026. sec.gov
- JERA, "JERA, Dell Technologies and RHAELM Sign MoU to Accelerate National-Scale AI Infrastructure Development in Japan", 1 October 2026. jera.co.jp
- Micron Technology, fiscal fourth-quarter 2026 results (Form 8-K, Exhibit 99.1), 30 September 2026. sec.gov
- Micron Technology, Fiscal Q4 2026 Earnings Call Prepared Remarks, 30 September 2026. micron.com
- Samsung Electronics, 3Q 2026 Pre-Earnings Guidance, 8 October 2026. samsung.com
- The Korea Times, "Samsung Electronics 1st Korean firm to top $80 bil. in quarterly operating profit", 8 October 2026. koreatimes.co.kr
- TSMC, September 2026 Revenue Report (Form 6-K), 8 October 2026. sec.gov
- Focus Taiwan (CNA), report on Lisa Su's remarks in Taipei, 6 October 2026. focustaiwan.tw
- Guru3D, "AMD Expects Substantial Chip Supply Increase in 2027, Lisa Su Says", 7 October 2026. guru3d.com
- ifeng.com, report on Huawei's Xu Zhijun and Ascend 950 capacity (Chinese), 7 October 2026. tech.ifeng.com
- The Online Citizen, "Parliament passes Digital Infrastructure Bill amid concerns over Singapore's data centre growth", 7 October 2026. theonlinecitizen.com
- Eco-Business, "Singapore sets Southeast Asia's first binding data centre rules, building demand for clean energy", 8 October 2026. eco-business.com
- Eco-Business, "Data centre boom creates investment risk for Malaysia's power system", 7 October 2026. eco-business.com
- The Edge Malaysia, "Anwar's Budget 2027 speech", 9 October 2026. theedgemalaysia.com
- Silicon UK, "Data Centre Proposed For Site Of Microsoft's UK Headquarters", 7 October 2026. silicon.co.uk
- The Register, "Power approval set to delay Oracle's Wisconsin AI datacenter", 2 October 2026. theregister.com
- investingLive, "Oracle trucks in natural gas to keep AI data centres on schedule as pipelines lag", 9 October 2026 (on a Bloomberg report of 8 October). investinglive.com
- The Star (Reuters), "Goldman sees US data center growth intact despite opposition", 5 October 2026. thestar.com.my
- KUT, "Taylor annexes data center and power plant", 9 October 2026. kut.org
- Reuters via Zawya, "Global bond rout deepens, pushes US Treasury yields to 24-year peak", 1 October 2026. zawya.com
- The Next Web, "OpenAI is in talks with Abu Dhabi's MGX and BlackRock for a $30B round", 5 October 2026. thenextweb.com
- investingLive, "SpaceX seeks $40 billion in debt led by Apollo to fund Nvidia chip order, FT says", 7 October 2026. investinglive.com
About this brief
This brief was prepared by Vailinor Analysts to help people better understand the AI and energy spaces, and the places where the two meet: power for data centres, the chips that set how much power they draw, and the money and policy behind both. It covers 1 to 11 October 2026, plus items released after the US market close on 30 September, and is written as at 12 October 2026. Every figure comes from the public sources listed above, as reported by the companies, regulators and publications named, and forecasts are attributed to whoever made them. Nothing in it is investment advice.